How Long Does it Take to Build a Slitter Rewinder?

25 August 2023 - 13:13, by , in Converting Equipment and Machinery, Comments off

How to understand the factors that impact slitter rewinder delivery

Whether you’re doing research for a future purchase or you’ve already got the ball rolling, one of the most common questions we hear from customers is, “How long does it take to build a slitter rewinder?”

There’s no single answer for this question until you know the precise specifications of the machine you need—there are simply too many variables involved.

In this article, we’ll discuss:

  • The key factors that determine how long it will take to build a slitter rewinder
  • A typical timeline for building a slitter rewinder
  • The importance of working with a manufacturer you can trust

Factors that affect the timeline for building a slitter rewinder

When we provide customers with a projected timeline for their equipment, it’s calculated with these factors in mind:

Customization requirements

Slitter rewinders have a wide range of uses, from processing textiles for the apparel industry to foam and film for packaging. This means that every machine we build is slightly different from the next, as each of our customers has customization requirements to ensure that their slitter rewinder meets their needs.

The amount and type of customization needed for your machine will affect the timeline of the build process. For example, if a customer requests a unique customization that our team hasn’t done before, it will take time for us to plan the logistics of how to execute it and get the extra parts and materials needed to make it happen.

Size and complexity of the machine

Naturally, a larger or more complex slitter rewinder will take longer to manufacture than a more simple model. Slitter rewinders with complex requirements require a much longer timeline than a simpler build.

Availability of materials and components

There are also some factors that are largely out of our control—the availability of materials and components is one of them.

We use the highest quality materials and components to ensure that our machines are built for long-term performance, but it can take time for us to source these materials. During times when components are in high demand or there are production bottlenecks, like in the early days of the pandemic, it can take longer than anticipated to get what we need.

Number of orders in the production queue

Another factor is the number of orders in our production queue. We strive to prioritize all of our orders equally and ensure that customers receive their equipment when they want it, but if we have a high volume of orders, it’s likely that our timeline for your slitter rewinder may be longer. Our goal is to always ensure that each machine is built to the highest standard, rather than rush the process.

Testing and quality assurance processes

Finally, no machine we produce leaves our facility without undergoing extensive testing and quality assurance processes; this ensures that every single slitter rewinder we build meets our exacting standards. The length of our QA process can vary depending on the complexity and customization requirements of the machine, as well as the industry it will be used in.

Typical timeline for building a slitter rewinder

While the factors above impact the projected timeline for a slitter rewinder, here’s a general outline of what the process typically looks like.

Overview of the production process

1. Design and engineering phase (4 weeks)

During this phase, our team will review your requirements and determine the best design to meet your needs. We will also order any additional materials or components needed for the build and create detailed schematics of the machine.

2. Manufacturing phase (12 weeks)

This is when the actual construction begins. Our expert technicians assemble the individual components and weld them together to form your custom slitter rewinder.

3. Quality assurance and testing (4 weeks)

The final step in the process is testing the performance of your machine, validating that it meets all customer requirements, and verifying that it meets all industry standards. Our QA team also conducts testing to ensure that our slitter rewinders are reliable, functioning properly, and built for long-term performance.

4. Delivery preparation (2 weeks)

Once our team is satisfied that the machine meets all requirements, we will prepare it for delivery.

Potential delays and how they can impact the timeline

There are a few factors that can cause potential delays in the production of slitter rewinders:

  • Last-minute customization requirements
  • Limited availability of components or materials
  • Unexpected problems that require additional time to resolve

The bottom line

The process of building a custom slitter rewinder is complex and requires careful attention to detail. It typically takes approximately 22 weeks from the initial design and engineering phase to the final delivery, but there are a number of factors that impact our projected timeline for delivery.

When you purchase a slitter rewinder from an experienced manufacturer, not only will you have a clearer picture of when your equipment will be delivered, you can also rest assured that the machine is built correctly and ready to stand the test of time.

For a reliable, American-made slitter rewinder built to your exact specifications, contact Pinnacle Converting today.

About author:
Pinnacle Converting Equipment of Charlotte, NC has been designing and building slitting machines, sheeting machines, and custom converting equipment since 1995.